Skip to content

Hampton Inn Warroad, Construction Updates

Hampton Inn Warroad, MN

April 23, 2021 UPDATE:
It’s exciting on property right now, as the pool slides are ready to be installed, furniture is being placed, and final touches are progressing! We will open to overnight guests in the next month and look forward to inviting local community members to enjoy our on-site bar/restaurant and other unique amenities.

Amenities:

  • Breakfast included, with hot options (Pending COVID-19 restrictions)
    • Breads, bagels, yogurt, juice, cereal, eggs, sausage, waffles, etc.
  • Large pool area
    • Spiral slide to standard pool
    • Beaver-shaped slide in zero-depth pool
    • Hot tub
  • Floor hockey room with real boards and players’ box
  • Deluxe fitness room
  • Bar/restaurant on-site
  • Rooftop and ground floor patios
  • Conference room and larger meeting room

APRIL 14, 2021 UPDATE:

MARCH 29, 2021 UPDATE:
The Beaver Slide for the Kiddie Pool has arrived!

MARCH 25, 2021 UPDATE:
The Hockey Room construction has begun!
Hampton Inn Warroad, MN

MARCH 16, 2021 UPDATE:
“As the furniture is being put into place, our team is getting more excited everyday! It won’t be much longer before we can welcome you to your home away from home! Watch for our Grand Opening date to be announced soon!”

MARCH 2, 2021: UPDATE
The new light fixtures.

FEBRUARY 26, 2021
How great is this Front Desk?

FEBRUARY 18, 2021 UPDATE:
Window treatments, public space business nooks, pool progress, public space flooring and more!

FEBRUARY 3, 2021 UPDATE:
First Floor flooring is underway

 


DECEMBER 30, 2020
“Unfortunately, due to COVID-19 and weather setbacks, we are experiencing a delay in our opening date. We will update as we learn more, but look for our NEW grand opening to happen late February. We appreciate your excitement and support and can not WAIT to welcome our first guests!”

 


NOVEMBER 20, 2020 UPDATE:
Pool area is coming along!

OCTOBER 28, 2020 UPDATE:
The Hampton Inn Warroad building is taking shape! Doors are installed, bathroom vanities, laundry equipment, more wallpaper – and the best part, a warm building!
Hampton Inn Warroad

OCTOBER 12, 2020 UPDATE:
Doors, wallpaper and more being installed.
Hampton Inn Warroad, MN

SEPTEMBER 13, 2020 UPDATE:
Roughly 3 months away from opening!
Curbing this week, parking lot next week and indoor tile coming soon.

Hampton Inn Warroad, MN

 